phase, plan, subsystem, tags, requires, provides, affects, tech-stack, key-files, key-decisions, patterns-established, issues-created, duration, completed
phase
plan
subsystem
tags
requires
provides
affects
tech-stack
key-files
key-decisions
patterns-established
issues-created
duration
completed
07-testing-documentation
01
docs
documentation
readme
project-completion
phase
provides
06-validation-reports
validation command and completeness metrics
Scripts/README.md with pipeline documentation
PROJECT.md with completion status
future-maintenance
onboarding
Documentation-only final phase (validation reports sufficient for testing)
Comprehensive README with architecture diagram and module reference
2 min
2026-01-10
Phase 7 Plan 01: Documentation & Finalization Summary
Scripts/README.md with pipeline overview, architecture diagram, and module reference; PROJECT.md updated with all requirements marked complete
Performance
Duration: 2 min
Started: 2026-01-10T16:41:56Z
Completed: 2026-01-10T16:43:38Z
Tasks: 2
Files modified: 2
Accomplishments
Created comprehensive Scripts/README.md with Quick Start, Architecture diagram, and Module Reference
Updated PROJECT.md with all Active requirements marked complete (7 items)
Updated Key Decisions table with outcomes for all 3 decisions
Updated Current State to reflect resolved data quality and complete pipeline
Task Commits
Each task was committed atomically:
Task 1: Create Scripts/README.md - d9f446b (docs)
Task 2: Update PROJECT.md - f1adaf3 (docs)
Files Created/Modified
Scripts/README.md - Pipeline overview, architecture, module reference, commands
.planning/PROJECT.md - Marked all requirements complete, updated decisions and current state
Decisions Made
None - followed plan as specified.
Deviations from Plan
None - plan executed exactly as written.
Issues Encountered
None.
Next Step
Phase 7 complete. Milestone complete.
Phase: 07-testing-documentation
Completed: 2026-01-10