docs(09-03): complete scenario C corridor efficiency TDD plan

Phase 9 complete: All three trip planner modes validated with TDD.

Summary of 09-03 accomplishments:
- Feature 1: Corridor game inclusion (5 tests, 1 fix)
  - Enhanced findDirectionalStadiums() to exclude beyond-endpoint games
- Feature 2: Anti-backtracking validation (7 tests, all passed)
  - Confirmed existing implementation validates monotonic progress

12 tests added, 3 commits (2 test, 1 feat).

State updates:
- Progress: 30% → 40%
- Phase 9: Complete (3/3 plans)
- Next: Phase 10 (Trip Builder Options TDD)

Co-Authored-By: Claude Sonnet 4.5 <noreply@anthropic.com>
This commit is contained in:
Trey t
2026-01-10 15:43:23 -06:00
parent b6f11a46dc
commit 1d7a7d9cbe
3 changed files with 116 additions and 8 deletions

View File

@@ -50,7 +50,9 @@ Plans:
**Goal**: Test game scheduling (by dates), must-see games inclusion, start/end cities routing
**Depends on**: Phase 8
**Research**: Unlikely (internal patterns)
**Plans**: TBD
**Plans**: 3
**Status**: Complete
**Completed**: 2026-01-10
Test expectations:
- By Dates: Game scheduling fits date range, no conflicts, date boundaries respect timezone
@@ -60,7 +62,20 @@ Test expectations:
Plans:
- [x] 09-01: Scenario A timezone & conflict TDD — completed 2026-01-10
- [x] 09-02: Scenario B filler conflict TDD — completed 2026-01-10
- [ ] 09-03: Scenario C corridor routing TDD
- [x] 09-03: Scenario C corridor efficiency TDD — completed 2026-01-10
#### Phase 9.1: Fix Flaky Test When Ran In Parallel (INSERTED)
**Goal:** Resolve test suite flakiness where tests pass individually but fail in parallel execution
**Depends on:** Phase 9
**Research:** Unlikely (Swift Testing isolation patterns)
**Plans:** 0 plans
Plans:
- [ ] TBD (run /gsd:plan-phase 9.1 to break down)
**Details:**
5 tests fail in full suite but pass individually due to Swift Testing parallel execution + simulator state pollution (discovered in Phase 9 plans 01-02). This phase addresses the root cause to ensure reliable CI/CD testing.
#### Phase 10: Trip Builder Options TDD
@@ -115,6 +130,7 @@ Plans:
| 7. Testing & Documentation | v1.0 | 1/1 | Complete | 2026-01-10 |
| 8. DAG System TDD | v1.1 | 2/2 | Complete | 2026-01-10 |
| 9. Trip Planner Modes TDD | v1.1 | 2/3 | In progress | - |
| 9.1. Fix Flaky Test When Ran In Parallel | v1.1 | 0/? | Not started | - |
| 10. Trip Builder Options TDD | v1.1 | 0/? | Not started | - |
| 11. Itinerary & Constraints TDD | v1.1 | 0/? | Not started | - |
| 12. Integration Validation | v1.1 | 0/? | Not started | - |